Entity — person
Richard J. Melanson
By this entity
Filter & sort
No matching items.
49 matters on the record
Matters involved in
M130592026
→
M130422026
→
M128872026
→
M128822026
→
M128702026
→
M128432026
→
M128212026
→
M127952026
→
M127862026
→
M127842026
→
M127832026
→
M127682026
→
M127492026
→
M127432026
→
M127372026
→
M127172026
→
M127142026
→
M126942026
→
M126862026
→
M126852026
→
M126612025
→
M126232025
→
M126192025
→
M126112025
→
M126002025
→
M125902025
→
M125772025
→
M125512025
→
M125502025
→
M125082025
→
M124992025
→
M124572025
→
M124552025
→
M124362025
→
M123492025
→
M123382025
→
M122732025
→
M122472025
→
M122402025
→
M121862025
→
M121492025
→
M116892024
→
M116772024
→
M116302024
→
M113072023
→
M111082023
→
M110942023
→
M105692022
→
M088882018
→
Wasoqonatl Transmission Incorporated (WTI) – Q2 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
Closed
Procurement Administrator - Power Advisory - Application for Approval of the Green Choice Power Purchase Agreement
Open
Nova Scotia Power Inc. - 2025 Short Run Marginal Cost (SRMC) Test to Rates Report
Closed
North American Electric Reliability Corporation (NERC) - First Quarter 2026 - Application for Approval of Reliability Standards
Open
Wasoqonatl Transmission Incorporated (WTI) – Q1 2026 Independent Engineer Reporting: NS-NB Reliability Intertie Tie Project
Closed
Nova Scotia Power Inc. CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 (P&A)2026 Q1 Capital Reports
Closed
EfficiencyOne - 2025 Inter-Affiliate Code of Conduct Annual Compliance Report
Closed
Town of Berwick Electric Commission - Factorydale Hydropower Plant Refurbishment - $6,000,000
Closed
Nova Scotia Power Inc. - 2025 Storm Restoration Cost Report
Closed
Nova Scotia Power Inc. - 2025 Annual Performance Standards Report
Open
Nova Scotia Power Inc. - Regulation 3.6 - 2025 Net Metering Report
Closed
Nova Scotia Power Inc. - Extra Large Industrial Active Demand Control Tariff (ELIADC) - 2025 Annual Report
Closed
NSPI DRO Appeal - Billing Issues - Christine Cameron
Open
Nova Scotia Power Inc. - CI C0068714 – IT – Identity & Access Management - $6,756,522
Open
NSPI DRO Appeal - Billing Issues - Emily Martin
Closed
North American Electric Reliability Corporation (NERC) - Fourth Quarter 2025 - Application for Approval of Reliability Standards
Open
NSPI DRO Appeal - Billing Issues - Jessica Pelley
Closed
Nova Scotia Power Inc. - Cold Weather Event, January 23-26, 2026
Closed
Nova Scotia Power Inc. - Community Solar Program – 2025 Report
Closed
Nova Scotia Power Inc. - Green Choice Program – 2025 Reporting Requirements
Closed
Nova Scotia Power - Application for approval of an Above-the-Line Tariff applicable to Port Hawkesbury Paper (PHP)Application for approval of the Extra Large Industrial Dispatchable (ELID) Tariff, an above-the-line- tariff available to Port Hawkesbury Paper
Open
Northeast Power Coordinating Council (NPCC) - Fourth Quarter 2025 for Approval of Revised Regional Reliability Criteria
Closed
Nova Scotia Power Inc. - 2026 Annual Capital Expenditure (ACE) Plan - $284 million
Closed
NSPI DRO Appeal - Solar Billing Process - David Rossiter
Closed
Nova Scotia Power - Cybersecurity Accountability IN THE MATTER OF AN INQUIRY about the impact of the cyber incident on NOVA SCOTIA POWER INCORPORATED’s collection and retention of customer information, customer service and communications, billing processes and regulatory matters
Open
Nova Scotia Power Inc. - CI C0070486 – HYD Lower Great Brook Stoplog Replacement – $3,593,884
Closed
North American Electric Reliability Corporation (NERC) - Third Quarter 2025 - Application for Approval of Reliability Standards
Closed
Nova Scotia Power Inc. - 2026 Annually Adjusted Rates (AARs)
Closed
To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
Closed
Nova Scotia Power - CI C0080112 – HYD Big Falls Unit 6 Rotor Re-Insulation (U&U) - $1,025,626
Closed
Nova Scotia Power Inc. - Application for approval of 2025/26 Time Varying Pricing (TVP) Tariffs
Closed
NSPI Complaint - Systemic Regulatory Compliance Issues - Blarney Stone RestaurantThe complainant wishes to clarify that their complaint is not related to a billing error, which has already been resolved directly with Nova Scotia Power. Rather, the concern is with broader systemic issues regarding NSP’s billing and metering practices under Board-approved tariffs. The complainant notes that some of NSP’s demand meters cannot be manually reset, which affects the correct application of rates. Additionally, customers with variable seasonal demand are disadvantaged when demand is estimated or carried forward without resetting the demand register.
Closed
Nova Scotia Power Inc. - CI C0059783 – HYD Upper Lake Falls 2 Overhaul – $1,582,014
Closed
North American Electric Reliability Corporation (NERC) - Second Quarter 2025 - Application for Approval of Reliability Standards
Closed
Nova Scotia Power Inc. (NSPI) - 2025 Load Forecast Report
Closed
NSPI DRO Appeal - Smart Meter Issues - Sherry Dennis
Closed
Board Inquiry into Nova Scotia Power's Cybersecurity Incident
Open
Nova Scotia Power Inc. - Evergreen IRP Action Plan & Roadmap Update
Closed
EfficiencyOne - 2024 Affiliate Code of Conduct Annual Compliance Report
Closed
EfficiencyOne - 2024 DSM Annual Progress Report and 2024 DSM Evaluation Reports
Closed
Nova Scotia Power Inc. - Investigation arising from Joint Use Agreement between NS Power and Bell Aliant
Closed
Nova Scotia Power Inc. (NSPI) - 2024 Load Forecast Report
Closed
EfficiencyOne - 2023 Audited Financial Statements - December 31, 2023
Closed
EfficiencyOne - 2023 DSM Annual Progress Report and 2023 DSM Evaluation Reports
Closed
P-884 - Nova Scotia Power Inc. - 2023 Evergreen Integrated Resource Plan (IRP) - Action Plan and Roadmap
Closed
P-194 - Nova Scotia Power Inc. (NSPI) - 2023 Load Forecast Report
Closed
E-ENS-F-23 - EfficiencyOne - 2022 Audited Financial Statements - December 31, 2022
Closed
P-194 - Nova Scotia Power Inc. (NSPI) - 2022 Load Forecast Report
Closed
E-ENS-G-18 - EfficiencyOne - Evaluation of DSM Programs - Application to allow inclusion of Non-Energy BenefitsEfficiencyOne - Application for approval of the use of Non-Energy Benefits within Cost-Effectiveness Testing
Closed