HomeMattersM12593
M12593 Closed Electricity

Nova Scotia Power Inc. - CI C0053696 – ECC Wind Integration - $4,428,335

Filed 12/01/2025 14 documents

The filings themselves

Documents

Key documents 1 file
  • 101069 Board Decision Letter PDF · 02/26/2026
Exhibits 3 files
  • N-1 Application PDF · 12/01/2025
  • N-2 NSPI (NSEB) RIR 1 to 22 - Redacted PDF · 01/23/2026
  • N-2(C) NSPI (NSEB) RIR 1 to 22 - Confidential PDF · 01/23/2026
Other documents 10 files
  • 100139 Letter NSPI re: Capital Items Filed Outside the Quarter Package PDF · 12/01/2025
  • 100188 Board Letter re: Asking is NSIESO would like to participate in the proceeding PDF · 12/03/2025
  • 100232 Letter from NSIESO re participating in matter PDF · 12/08/2025
  • 100242 Board Letter re: Timeline PDF · 12/09/2025
  • 100475 Letter NSIESO re: does not intend to issue IRs or provide comments PDF · 01/05/2026
  • 100501 NSEB (NSPI) IR-1 to IR-22 - PDF PDF · 01/07/2026
  • 100502 NSEB (NSPI) IR-1 to IR-22 - WORD DOCX · 01/07/2026
  • 100704 Letter NSPI re: RIRs and request confidentiality PDF · 01/23/2026
  • 100893 Letter NSPI re: No reply comments PDF · 02/10/2026
  • 101069 Board Decision Letter PDF · 02/26/2026

What's discussed — click to drill in

Topics

Renewable Energy
32 passages across 6 documents
Generator Interconnection
23 passages across 7 documents
Regulatory Approval Processes
19 passages across 10 documents
Capital Expenditures
15 passages across 6 documents
Power Purchase Agreement
14 passages across 6 documents
Infrastructure Planning
13 passages across 5 documents
Generation Grid Resources
12 passages across 5 documents
Energy Management Information Systems
11 passages across 4 documents
Grid Modernization
8 passages across 6 documents
System Reliability
7 passages across 4 documents
2025 Ace Plan
6 passages across 4 documents
Energy Efficiency
6 passages across 4 documents
Cost Considerations
5 passages across 3 documents
Rates And Money
5 passages across 3 documents
Capacity Market Participation
4 passages across 2 documents
Cost Recovery
4 passages across 4 documents
Energy Storage
3 passages across 2 documents
Operating Expenses
3 passages across 3 documents
Project Schedule
3 passages across 3 documents
Affordability
2 passages across 2 documents
Capacity Costs
2 passages across 1 documents
Distribution Planning
2 passages across 1 documents
Energy Efficiency Budgets
2 passages across 2 documents
Integrated Resource Plan
2 passages across 2 documents
Procurement Practices
2 passages across 2 documents
Regulatory Compliance
2 passages across 2 documents
Accounting Policies
1 passages across 1 documents
Asset Management
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Confidentiality
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Electricity Generation
1 passages across 1 documents
Energy Efficiency Financing
1 passages across 1 documents
Energy Efficiency Resource Assessment Model
1 passages across 1 documents
Financial Instruments
1 passages across 1 documents
Information Disclosure
1 passages across 1 documents
Program Evaluation
1 passages across 1 documents
Public Utilities Act Nova Scotia
1 passages across 1 documents
Transmission Planning
1 passages across 1 documents