Nova Scotia Power Inc. CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 (P&A)2026 Q1 Capital Reports
What's happened
Filing Timeline
-
06 Aug
DecisionNSEB issues decision letter approving Nova Scotia Power's $2,431,095 L7005 Canso Crossing Vibration Mitigation project as a Planned and Advanced Capital expenditure
-
14 Jul
RIRNova Scotia Power filed responses to four Board information requests on the $2.43M Canso Crossing vibration mitigation capital project, addressing cost breakdowns, engineering report status, work phasing, and original design rationale.
-
22 Jun
DocumentNSEB Board Staff issued four Information Requests to Nova Scotia Power regarding the $2,431,095 Canso Crossing Vibration Mitigation capital project application
-
19 Jun
DocumentNova Scotia Power files redacted version of Canso Crossing vibration mitigation application after NSEB queries confidentiality scope of 247-page technical attachment
-
19 Jun
DocumentNova Scotia Power refiled confidential capital application for Canso Crossing Vibration Mitigation project after NSEB requested clarification of confidentiality designation for Attachment 1
-
04 May
DocumentNova Scotia Power filed a Planned & Advanced capital project application seeking NSEB approval for $2,431,095 in completed transmission works to mitigate Aeolian vibration damage on the L7005 Canso Strait crossing.
The filings themselves
Documents
Key documents
1 file
- 103095 Decision Letter
Exhibits
6 files
- N-1 CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 - Redacted
- N-1(C) CI C0044172 – L7005 Canso Crossing Vibration Mitigation - $2,431,095 - Confidential
- N-2 CI C0044172 REFILE - Redacted
- N-2(C) CI C0044172 REFILE - Confidential
- N-3 NSPI (NSEB) RIR 1 to 4 - Redacted
- N-3(C) NSPI (NSEB) RIR 1 to 4 - Confidential
Other documents
5 files
- 101854 Letter NSPI re:First Quarter 2026 Capital Items
- 102450 Letter NSPI re: Confidentiality
- 102455 NSEB (NSPI) IR 1 to 4
- 102749 Letter NSPI re: RIRs & Justification for partially confidential material
- 103095 Decision Letter
What's discussed — click to drill in
Topics
Infrastructure Planning
45 passages across 5 documents
Generation Grid Resources
32 passages across 4 documents
Capital Expenditures
20 passages across 7 documents
Distribution Planning
13 passages across 2 documents
Generator Interconnection
12 passages across 3 documents
Power Infrastructure
11 passages across 1 documents
System Reliability
9 passages across 6 documents
Distribution
8 passages across 2 documents
Grid Modernization
8 passages across 2 documents
Transmission Planning
7 passages across 2 documents
Cost Considerations
6 passages across 3 documents
Energy Efficiency Resource Assessment Model
6 passages across 1 documents
Asset Management
4 passages across 2 documents
Confidentiality
4 passages across 3 documents
Capacity Costs
3 passages across 3 documents
Energy Efficiency
3 passages across 1 documents
Planned Outage
3 passages across 2 documents
Rates And Money
3 passages across 2 documents
Regulatory Approval Processes
3 passages across 2 documents
Regulatory Oversight
3 passages across 3 documents
Cost To Customer
2 passages across 2 documents
Energy Efficiency Budgets
2 passages across 1 documents
Jurisdictional Questions
2 passages across 2 documents
Project Schedule
2 passages across 2 documents
Renewable Energy
2 passages across 1 documents
Stakeholder Engagement
2 passages across 2 documents
Accounting Standards
1 passages across 1 documents
Affordability
1 passages across 1 documents
Climate Adaptation
1 passages across 1 documents
Cost Deferral
1 passages across 1 documents
Cost Effectiveness
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Cybersecurity
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Electricity Generation
1 passages across 1 documents
Energy Efficiency Financing
1 passages across 1 documents
Energy Efficiency Resource Standards
1 passages across 1 documents
Energy Management Information Systems
1 passages across 1 documents
Environmental Compliance
1 passages across 1 documents
Information Disclosure
1 passages across 1 documents
Procurement Practices
1 passages across 1 documents
Public Interest
1 passages across 1 documents
Rate Design
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents