Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
What's happened
Filing Timeline
-
Document—
-
15 Oct
RIRNova Scotia Power filed responses to Board IR-19 through IR-24 (3rd Set) on the L5031 Hubbards to East Chester project, explaining mobile transformer availability and the need for bypass structures
-
25 Sep
DocumentNSEB grants Nova Scotia Power a two-week extension to respond to Round 3 Information Requests in the Hubbards to East Chester L5031 capital project proceeding
-
17 Sep
DocumentNSEB Board Staff issues 3rd set of Information Requests (IR-19 to IR-24) to Nova Scotia Power on L5031 Hubbards to East Chester line replacement project
-
14 Sep
RIRNova Scotia Power filed responses to NSEB Round 2 Information Requests (IR-11 to IR-18) on the L-5031 Hubbards to East Chester transmission line replacement project, disclosing project completion targeted for December 2026 and correcting a $1M typographical error in the ATO application.
-
28 Aug
DocumentNSEB Board Staff issues second set of information requests to Nova Scotia Power on the $6.96M L5031 Hubbards to East Chester transmission replacement application
-
24 Aug
RIRNova Scotia Power filed responses to NSEB Information Requests 1–10 on the $6.96M L5031 Hubbards to East Chester transmission line replacement project, disclosing mobile substation removal, bypass structure costs, and construction progress.
-
30 Jul
DocumentNSEB Board Staff issued 10 information requests to Nova Scotia Power regarding the L5031 Hubbards to East Chester transmission line replacement project, seeking justification for a $6,957,058 ATO application that significantly exceeds prior ACE Plan estimates.
-
13 Jul
DocumentNova Scotia Power filed an Authorization to Overspend application for the L5031 Hubbards to East Chester 69kV transmission line replacement, seeking approval for $1,659,474 in cost overruns above the approved $5,297,584 budget.
The filings themselves
Documents
Exhibits
6 files
- N-1 CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058
- N-2 NSPI (NSEB) RIRs 1-10 - Redacted
- N-2(C) NSPI (NSEB) RIRs 1-10 - Confidential
- N-3 NSPI (NSEB) RIR 11 to 18 - Redacted
- N-3(C) NSPI (NSEB) RIR 11 to 18 - Confidential
- N-4 NSPI (NSEB) RIR 19 to 24
Other documents
9 files
- 102746 Letter NSPI re: Capital Items Filed Outside the Quarter Package
- 103025 NSEB (NSPI) IR-1 to IR-10
- 103305 NSPI letter enclosing RIRs and request for confidentiality
- 103363 NSEB (NSPI) IR 11 to 18
- 103567 Letter re: RIRs and Request for Confidentiality
- 103604 NSEB (NSPI) IR 19 to 24
- 103705 NS Power Letter re: extension request
- 103706 Board letter approving extension request
- 103921 Letter NSPI re: RIRs
What's discussed — click to drill in
Topics
Infrastructure Planning
26 passages across 8 documents
Capital Expenditures
16 passages across 5 documents
Regulatory Approval Processes
12 passages across 10 documents
2025 Ace Plan
7 passages across 4 documents
Distribution Planning
7 passages across 5 documents
Transmission Planning
7 passages across 5 documents
Project Schedule
6 passages across 4 documents
Power Infrastructure
5 passages across 3 documents
Cost Considerations
4 passages across 3 documents
Distribution
4 passages across 4 documents
Right Of Way
3 passages across 3 documents
Cost Deferral
2 passages across 2 documents
Information Disclosure
2 passages across 2 documents
Rates And Money
2 passages across 2 documents
System Reliability
2 passages across 2 documents
Unplanned Outage
2 passages across 2 documents
2023-2026 DSM Plan
1 passages across 1 documents
2026 DSM Extension
1 passages across 1 documents
Accounting Standards
1 passages across 1 documents
Asset Management
1 passages across 1 documents
Capacity Costs
1 passages across 1 documents
Confidentiality
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Emergency Response
1 passages across 1 documents
Generation Grid Resources
1 passages across 1 documents
Jurisdictional Questions
1 passages across 1 documents
Planned Outage
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
Regulatory Oversight
1 passages across 1 documents
Stakeholder Engagement
1 passages across 1 documents